Completed by the contractor. Assists in tracking and reviewing contractor performance and in identifying areas requiring corrective...
Forms & Documents
Conducted after project is completed. Includes a review of:
- Pre-Start Contractor Inspection.
- Incidents reported...
List of all contractors approved to work for NTPC. Currently under revision.
Follow the NTPC Contractor Discipline Policy if and when Safe Work Practices and/or Safe Job Procedures are not being followed and/or...
A Work Permit is a guarantee of isolation for specific work on specific apparatus.
To be used to document Work Protection Code training.
The Local Issuing Authority shall obtain permission from the System Issuing Authority prior to issuing permits on apparatus connected to...
The Issuing Authority shall record the first permit transfer in the Transfer section of the permit, and any additional permit transfers...
A Work & Test Permit is a guarantee of de-energization when issued under which specific work and tests are done on specific...
A Hold-Off Permit is a guarantee of non-reclose for work on or near dynamically alive apparatus.